TIE-DOWNS - METAL ROOFS, MAJOR STRUCTURAL DEFECTS AND PRE-PURCHASE BUILDING INSPECTIONS

Important information for sellers and buyers of properties with metal roofs in Western Australia - incl. information relating to roof tie-downs and strapping.


There are unique issues associated with metal roof cover and timber roof frames which may give rise to major structural defects, potentially impacting the sale of houses in WA.


Background

When tiles were the common roof cover material the roof frame was also about holding up the weight of the roof/tiles or in short, managing downward forces. With the reintroduction of metal roof covering, the significant weight has been removed and hence the issue is now about containing uplift forces generated by wind passing over and through a house. In essence these light weight roofs can now act like the wing of a plane or the sail on a yacht. Tiles on the other hand, are much heavier.


For in excess of 20 years, the Building Code of Australia and the Australian Framing Code (AS-1684) has required that the timber in the roof frames and then the overall roof frame itself must be very firmly tied together and then tied to the building structure through a series of metal straps, propriety brackets, rods and bolts. The essence of all of this strapping, tying and bolting is to ensure that the house can hang on to the roof and roof cover during a significant storm. In fact, the Australian Standards refers to a one in a one hundred year storm that WA (ex-cyclone areas) in particular Perth, has not yet experienced.


DMIRS (formally the WA Building Commission) published a report in 2016 (COMPLIANCE REPORT: A summary of technical building inspections 2015-16) which indicated that of 651 roof inspections undertaken by the Commission, 37% were unsatisfactory. The findings were updated in Mid-year 2016/17 and published. Positively the overall position improved, sadly 33% were still unsatisfactory. The key takeout and based on these numbers, is that almost 1 in 3 metal roof homes could be adversely impacted by this issue.


The Problem

The problem is that every week at Superstruct we identify several homes across Western Australia where this key strapping, tying and bolting of important structural elements has simply not been undertaken! At the time of the inspection, the roof has not failed but it is not compliant and in the event of a significant storm it is quite possible (according to the Australian Standards) that significant damage or failure can occur. Where the strapping, tying and bolting is deficient on a metal roof property, the roof frame will be deemed to contain structural defects. If a contract to purchase has been entered into and the REIWA standard building inspection clause has been utilised, the transaction may face challenges.


The Fix

The positive news is that the deficient strapping, tying and bolting can all be fixed. Where it relates to the centre of the roof down to the underpurlins a good roof carpenter, under the guidance of a builder, should be able to fix most homes within a day possibly two. Where the issues lies at the perimeter walls where tied down straps and rods to the wall plate are missing it can take longer, rarely more than a week possibly two. In multi storey homes where access to the upper level roof can be a challenge, it can take several weeks. What is important to remember is that the issues can all be fixed, often for less than $2,000 rarely for more than $20,000.


Properties that can be particularly impacted by the above are older properties where there has been a tile to metal roof cover conversion. Theoretically, these conversions should have been undertaken via Council Approved Plans (inclusive of engineer’s plans) which would have called for the required roof frame strapping, tying and bolting to be retro fitted. Sadly, sometimes these conversions have been done without plans, approvals or a clear understanding of the core requirements.


The Frustration

The challenge with all of the above is that building inspections in WA are often undertaken post finance approval and often only weeks prior to the proposed settlement date. Trying to organise builders and roof carpenters to complete remediation work, while you are trying to organise moving house, can be a very challenging task. At its worst, the remedial work may delay settlement which can wreak havoc on all of the stakeholder plans.


Some Potential Solutions

  1. Get the building inspection completed as early as possible

  2. Where a roof frame issue is identified act quickly and decisively to get the issue resolved by engaging a builder as soon as possible

  3. If the property is less than 6 years old from practical completion, the original builder is obliged to resolve the issue unless they can produce plans from an engineer negating the requirement (quite rare). The challenge being to get the original builder to act in the required time (i.e. pre settlement). Important to note that the builder’s obligation carries onto whoever owns the property so it is possible that the buyer simply progress with the transaction and makes a claim against the original builder, but this can be a little messy for the new owner.

  4. Get quotes from one or several Builders to undertake the work, do a contract price adjustment, proceed to settlement and remediate post purchase. Another good potential solution, however the buyer needs to ensure that the quote and supplier is solid to complete the work. Careful due diligence is required on the quote. Holding funds on trust until the work is completed is another potential solution but can get complicated

The Sellers Easy Solution for Sellers with Metal Roofs


The easiest solution is for sellers, particularly those with metal roofs to have a Building Inspection undertaken on their home before going to market. At Superstruct, for less than $600 on the average single level home, a building inspector can undertake a Building Inspection on a house for a seller so as to ensure that this and other similar structural issues may not exist in a home prior to taking the property to market. A small price to pay for assurance when trying to sell your home.


More Information

If the above is of interest to you regarding roof framing issues, the Department of Mines, Industry Regulation and Safety (DMIRS) (formally the WA Building Commission) has produced an excellent video.



The link below contains information that addresses common construction issues identified through ongoing building audits as well as concerns and queries raised by various stakeholders in the Western Australian building industry.


It also addresses concerns that the current Building Code of Australia and referenced Australian Standards do not have a simple deemed-to-satisfy solution for the WA construction practice of attaching tie-down straps to timber roof/over battens.


The following information has been collated by Building and Energy in collaboration with a recognised expert in timber and wind engineering. It supplements information provided in Australian Standard AS 1684.2: 2010 – Residential timber-framed construction; Part 2: Non‑Cyclonic Areas (AS 1684.2).